University of Utah - The Football Center
Training Verification
TSN Equipment Trained On Training Date Download
35302
Fire Suppression
7/25/2013
35303
Panelboards, Surge Suppression, Main Distribution
7/25/2013
35304
Generator/ATS
8/1/2013
35305
Network Lighting Controls
8/1/2013
35306
Occupancy Sensors
8/1/2013
35307
Fire Alarm
7/26/2013
35308
UPS System
7/26/2013
35309
Building Controls
7/26/2013
35310
Audio/Video Systems
7/22/2013
35311
Makeup Air Units
7/23/2013
35312
Exhaust Fans, Relief Fans and Transfer Fans
7/23/2013
35313
VFD
7/23/2013
35314
Rooftop Units
7/23/2013
35315
Cooling Tower
7/23/2013
35316
Inline Solid Separator
7/23/2013
35317
Air Handler
7/23/2013
35318
Water Treatment
7/23/2013
35319
Chiller
7/23/2013
35320
Split System
7/22/2013
35321
Pumps
7/22/2013
35322
Cabinet Unit Heaters
7/22/2013
35323
Plumbing System
7/22/2013
35323-2
DW/HW Storage Tanks
7/22/2013
35323-3
HVAC Piping
7/22/2013

 

Letter of Transmittal
Company Signature Delivery Date Download
Utah New Vision Construction
Wired Legacy